Summary Timeline - Day 4
| DATE TIME (CST)
| DAY | MET | EVENT | | 12/19/99
10:18:00 AM
| 4 | 002/14:00:00 | FD04 Wakeup | | 12/19/99
12:18:00 PM
| 4 | 002/16:00:00 | EVA 1
Prep | | 12/19/99
1:48:00 PM
| 4 | 002/17:30:00 | EMU Purg/Prbrth
(:50) | | 12/19/99
3:03:00 PM
| 4 | 002/18:45:00 | EVA 1
Start | | 12/19/99
3:18:00 PM
| 4 | 002/19:00:00 | Initial
EVA Setup | | 12/19/99
4:18:00 PM
| 4 | 002/20:00:00 | "RSU #1,2,3
Changout" | | 12/19/99
7:03:00 PM
| 4 | 002/22:45:00 | Open NICMOS
Valves | | 12/19/99
7:18:00 PM
| 4 | 002/23:00:00 | AFT SHRD
Door Close | | 12/19/99
7:28:00 PM
| 4 | 002/23:10:00 | MFR Swap | | 12/19/99
7:38:00 PM
| 4 | 002/23:20:00 | VIK INST | | 12/19/99
8:48:00 PM
| 4 | 003/00:30:00 | Daily
Closeout | | 12/19/99
9:28:00 PM
| 4 | 003/01:10:00 | EVA 1
End A/L Pre Repress | | 12/19/99
9:48:00 PM
| 4 | 003/01:30:00 | Post EVA
W/H20 Rechg | | 12/19/99
10:18:00 PM
| 4 | 003/02:00:00 | RMS Extended
Park | | 12/19/99
10:48:00 PM
| 4 | 003/02:30:00 | EVA 2
Tool Config | | 12/20/99
12:03:00 AM
| 4 | 003/03:45:00 | Next Day's
EVA RVW | | 12/20/99
2:18:00 AM
| 4 | 003/06:00:00 | SLEEP
FD04 |
AFT SHRD - Aft Shroud
EMU - Extravehicular Mobility Unit
EVA - Extravehicular Activity
MFR - Manipulator Foot Restraint
NICMOS - Near Infrared Camera Multi-Object Spectrometer
RSU - Rate Sensor Units
RVW - Review
VIK - Voltage Improvement Kits
The summary timeline for this mission is based on the original launch
date and time of December 16, 1999 08:18 p.m. CST.
|